The material management measures of one row of the material management data, as the Material Management report calculates them, read from the stored material aggregates. Truck applications are counted; tow-plow applications and soft-deleted aggregates are not.
A measure that no activity contributed to is null, not zero. Zero means activity was recorded with a zero value. The units are the report's storage units: solid in grams, anti-ice and pre-wet in litres, distances in kilometres and durations as time spans.
Each material type is a code the spreader controller reported, for example 7 for sand. A code of -1 means the type was not reported. A row holds at most one type of each material, with the total, rate and rate distance of that type alone. When the data holds more than one type of a material, it is returned in several rows: the n-th row holds the n-th type of every material that has one, in ascending order of code. Types of different materials share a row only by their position and are otherwise unrelated.
Properties
antiIceRate
The distance-weighted average rate the spreader controller reported for anti-ice (liquid) material, in litres per kilometre.
The distance-weighted average rate the spreader controller reported for solid material, in kilograms per kilometre.
solidRateDistance
The distance MaterialManagementMeasures.solidRate was averaged over, in kilometres. To average rates across rows, weight each row's rate by this distance: the sum of rate times rate distance divided by the sum of rate distances.
Until the stored aggregates record the distance their own rate was averaged over, the spread distance of the aggregates that reported a rate stands in for it. It equals that distance whenever the controller reported a rate throughout the application.
The distance driven while applying the row's solid material type, in kilometres. The spread distances of the rows of one trip add up to the distance driven while applying solid material during it.
spreadTime
The time spent applying the row's solid material type. The spread times of the rows of one trip add up to the time spent applying solid material during it.